I am closing in on deploying the ZCM10 agent to our ZFD7 managed workstations. We have roughly 1600 workstations.

My question, should I be worried about overloading the server? I had planned to deploy the agent between 2:00 am and 3:00 am with ZFD7 starting the install randomly between those times.

So that comes out to 1600 workstations registering into our zone in an hour.
Should I scale that back and do less workstations over multiple days?