I am using Zenworks 7 and performing a Lights Out Distribution for Office 2007. I setup my Pre-Install for a Specific Day > 6:00 PM to 11:55 PM with 0 spread time.

Then I associate a group of workstation objects to the App Object and set it to Force Run.

If I begin setting this up earlier in the day, around 3 PM. Activity is beginning on some of the workstations about 20-30 minuets after I setup everything (Around 3:30 or so). It is behaving outside the schedule and I do not know why. Any ideas? I am using Console One to setup everything.