Soon to move to linux but I need more time & the current volume is very low
on space

I need to move PO & Domain to a larger volume

This is a Netware 6.5 server with GW8

I've run dbcopy (I'm using the -m switch for Migration later this month -
hopefully )

dbcopy /m /p /f data:gwpo gw:gwsys/gwpo
dbcopy /m /d /f data:gwdom gw:gwsys/gwdom

I know I need to change the path in consoleone and startup files

(1) Do I shutdown GW then change the paths or whilst GW is still running?
(2) Do I run the 2nd pass of Dbcopy with /s option after I change the path ?