What does "Process immediately if device unable to execute on
schedule" actually do?

ZCM 11.3.2 When installing software, I typically set a distribution
schedule, Date Specific. I pick a date and start/end time and I check
"Install immediately after Distribution". I also check "Process
immediately if device unable to execute on schedule". Works fine most
of the time. But occasionally it won't install. For example, I had
to re-image a laptop after replacing the hard drive. A couple bundles
setup this way did not install. I assumed that "Process immediately
if device unable to execute on schedule" meant if the start date was
past, and the bundle was not installed, then it should happen right
away. But it just sits there...the bundle is effective, but not
installed. What am I missing?

Ken

--------------------------------------------------------